Project in Pictures: The final phase of the Hobbs Ice Arena
project is completed with the rink floor construction
// by PATRICK NEWKIRK, CIT
FLOORED
30 / NOVEMBER.DECEMBER.2019 USICERINKS.COM
1
1.
Subfloor heat piping 70% complete. Cooling header trench
located in the foreground of the picture.
2
. Insulation layer 60% complete, cooling header trench again
located in the foreground.
3
. Installing pipe chairs over the vapor barrier.