Schneider Arena in Providence, Rhode Island, used their shutdown
period to complete a chiller room replacement project
CHILL OUT
by ERIC DURSIN, CIRM
1
PHOTOS: SCHNEIDER ARENA
[ A P R O J E C T I N P I C T U R E S ]
1.
All hoses
that connected
to the header
were replaced.
Connections were
sanded and hoses
double clamped.
2.
A new 15-foot deep
snow melt pit with
a gas shock access
door which will
handle the weight of
a full ice resurfacer.
Rubber tire tracks
were installed to
protect the studs and
the concrete.