PROJECT IN PICTURES Stamford Twin Rinks 5. Pipe fitters cutting away pipes to prepare for moving the old equipment out the door 6. It was definitely time to replace the old chiller barrel 7. Out with the old 8. Off to the scrap yard 38 / SEPTEMBER.OCTOBER.2026 USICERINKS.COM 5 6 Project Breakdown 7 8 Stamford, CT. FACILITY: Stamford Twin Rinks (Opened in November 1996) TOTAL CONTRACTORS: 11 PIPE REMOVED/REINSTALLED: 4,400 linear feet