The journey so far…
Smart meter trials &
blueprint
Foundations
Sustainable Solutions &
Testing
BAU & Business Wide Scale
Jan 20-Nov 21
Dec 21-Oct 23
Nov 23-Mar 25
Apr 25 onwards
• 3,000 meters
installed in series of
trails
• 3 solution providers
(NB-iOT, Arqiva
Network and
LoRaWAN®)
• Benefits case built
and Technology
selected
Project team of 2
• Building AMP8 plan
• MVP capabilities
• Billing
• GDPR
• Continuous flow
identification
• Maintenance
• Minimal Tec
change
Project Team of 3
• Early start AMP8
investment
• Long term
Enterprise
Architecture design
• First generation
capabilities
• Baseline
performance
• Learn quickly
Project Team of 12
• Exchange 1.4 Million
Meters
• Install 125,000
Meters
• Network built first,
meters second
• Established
consistent
performance
• Transition meters
and capabilities to
BAU teams
• Continuous
improvement of
capabilities
Project team of 20
July 24 –
September
24
October 24 –
December
24
January 25-
March 25
April 25-
Ongoing