Simple. Affordable. Transformative.
Installs and Performance
• The rollout plan is built to systematically install
meters road by road to drive efficiency
• The Network must be in place first, and tested,
before the meter is installed enabling Day1
benefit realisation
• Installations started in Dec-24 and now scaling
up to 1,000 meter installs per day
• 20,100 successfully installed
• With a Data Completeness of 93%
July 24 –
September 24
October 24 –
December 24
January 25-
March 25
April 25-
Ongoing